FORMWORK

Image
Execution of Works Fabrication of formwork Typical form work details to perform the shape, lines, levels, dimensions & quality of concrete surfaces of Beams, Columns, RC Wall & Slab are attached separately in attachments. Permanent brick wall form work will be used for lower ground floor beams, pile caps, sump walls and lift walls where the waterproofing will be done. (Pile caps will not be water proofed) Examples: Pile caps & beams in the sump will be formed with sump base for waterproofing. Ply wood form and brick form, both will be used in the sides of pile caps up to the bottom of ground beams, inner face of ground beams at main entrance & most of the structural elements in other areas in ground floor considering the sequence of water proofing and the sequence of concrete casting. Refer drawings 230M/FW/06 and sheet 1, 2 & 3 in the attachments Materials for Form Work GI pipes, form ties, threaded bars and P-cones will be used to tie & brace the form

METHOD PRE CONSTRUCTION TERMITE CONTROL TREATMENT

PRE CONSTRUCTION SOIL TREATMENT Pre Construction Soil Treatment implies laying down a chemical barrier to prevent termites from getting back and forth between wood and soil. Termites need wood for food and soil for moisture, so they constantly travel back and forth between wood and soil. Where this situation does not exist, termites build the “shelter tubes” (Mud tubes) to span foundation walls and other parts of the building that separate wood from the soil. Besides building the tubes in and over foundation walls, termites may also build them inside the walls if constructed of concrete blocks or other porous material. In the case of slab buildings, termites enter through expansion joints, cracks, opening for utility and service connections. EXECUTION & SEQUENCE OF WORK Stage I – Plinth Treatment Once the backfilling is completed and prior to lay the leveling screed of ground floor slab, Roding will be done along the edge of beams and on entire slab area at one meter cent

METHOD OF BRICK MASONRY WORK

Description Brick walls will be built for internal partition & as well as perimeter walls of the building. All brick walls will be constructed by maintaining the verticality of walls and the location of the wall as per the construction issued Architectural drawings / approved shop drawings for brick walls in each floor. While constructing the brick walls, opening for the doors, windows & services will be provided according to the dimensions of doors, windows & the dimensions for openings shown in the service drawings by allowing cement / sand plaster thickness of 15mm in each side of the opening. Method of Brick Masonry Method of brick will be described as follows, Construction of brick wall. Construction of stiffener columns, beams & lintels. Providing reinforcement anchors to the stiffener columns from the structural beams, walls & columns. Construction of brick wall Marking for brick walls & openings w

Rock Blasting

Image
1. Introduction and General Information This method statement provides the details of the materials, the equipment, the procedure and relevant documents related to the Rock Blasting activity, including the quality control verifications, the measurement verifications, and also the safety precautions to be implemented for this work. 1.1. Location of Works The location of the rock blasting works will be limited to selected areas bound within the Right of Way (ROW). 2. Materials The major materials used for the rock blasting works include, but are not limited to the following. Explosive Dynamite Electric Detonators Ammonium Nitrate Other Barricade Tapes Warning Boards Sand bags Metal plate 3. Equipment The major equipment used for rock drilling and blasting works include, but are not limited to the following. Jack Hammers Air Compressor Circuit tester Tamping rod Siren Tractor JCB Other minor tools

Method Statement for Access Constructions

Image
  1. Introduction and General Information This method statement provides the details of materials, equipment, procedure and relevant documents related to access construction, including quality control verifications, measurement verifications, and also the safety precautions to be implemented at site for this work. 1.1. Location of Works The location of the access constructions will be as given in the access schedule, or otherwise directed by the Engineer. 2. Materials The major materials used for the access construction, but are not limited to the following. Grade 25/20 concrete Plywood shutters Reinforcement steel Gunn y bags for curing Water Quarry dust for leveling bed 3. Equipment The major equipment used for the access construction, but are not limited to the following. JCB, and/or Backhoes, and/or Excavator Truck mixer Tractor & Trailer Poker vibrators Rammers / Plate Compactors Water Bowser Sampling & Testing Equipment Au

Method Statement for Road Marking

1. Introduction and General Information This method statement consists of construction procedures of Road Marking, including material & machineries to be used, method of constructions, quality control test & verifications, and also the safety precautions to be implemented at site. 1.1. Location of Works Road marking location will be decided as per the road marking drawings issued by the Engineer. 2. Materials The major materials used for the road marking. DJ Thermo line thermoplastic road marking materials. Glass beads. 3. Equipment The major equipment used for Road marking includes, but are not limited to the following. Road Marking Machine. Gas. Rope. Chisel. Cleaning equipment Small Tools. 4. Safety Management and Control Safety precaution will be taken complying with the Traffic & Safety Plan. Every precaution will be taken to avoid any accidents & damages to adjoining properties, workers, and road users. All workers will be advised t

Method Statement for Culvert Construction

1. Introduction and General Information This method statement consists of construction of culverts, including material & machineries to be used, casting & construction procedures, quality control tests & verifications, and also the safety precautions to be implemented. 1.1. Location of Works Locations will be as per the approved construction drawings. 2. Materials The major materials used for construction of culverts work, but are not limited to the following. 6” X 9” Rubble Concrete Small tools 3. Equipment The major equipment used for construction of culverts, but are not limited to the following. Tractor JCB Concrete vibrators Vibrating rammers Leveling instrument Other minor tools 4. Safety Management and Control Safety precaution will be taken complying with the Road Work Traffic Control Manual and as described follows. Every precaution will be taken to avoid any accidents & damages to adjoining properties, workers, and road users. All work