Preliminary work in road construction is surveying & leveling works. This consists of Traverse Survey, TBM Survey, and Centre Line Setting out, Centre Line marking, Cross Section Survey and Submittal of Drawings. Traverse Survey At the commencement of contract all the basic traverse points will be checked and if any are found to be missing or appear to have been disturbed, necessary arrangements should be made to re-establish the points and traverse survey is carried out after that. Establishing TBMS We did not use survey Department bench marks .The permanent concrete cube was selected to permanent bench mark. It height was assumed hundred meters. But this point is not sufficient for construction purposes. So reference to this point Temporary bench marks (TBM) should be established. TBMs are used to transfer reduce levels in road construction. Temporary bench marks should be established at the rate of four per km and also at or near all structures. When e...
Good work.....
ReplyDeleteBut mewa banna denne natoopo