Foundation Part 02

Image
Excavation For Pile Cap Shoring is provided around the proposed pile cap with 600mm working space. Excavation is carried out up to certain level by using backhoe. Then excavation was carried out manually. Excavation is very difficult below ground water level. De watering system should be provided. Excavation With Jcb Shoring Is Provided Difficulties in excavation below the ground water level. Difficult to remove the soil Need continuous de watering process Density of soil will increased Erosion or collapse of the sides of the excavation Pile Hacking Pile is casted up to above required level. Then it is broken up to required level. This is known as pile hacking. Top concrete is weaken so pile should be casted above required level. Normally height above required level, it is equal to the diameter of the pile. But during the concreting ensure the concreting whole pile, normally concreting the ground level. Then excavate soil and pile ...

Setting Out

  Setting out is done to locate the position of the structural parts as in the detailed drawing with geometrical construction. The setting out is done to locate pile position, pile cap, column position, beam bottoms and slab boundary in the site. Setting out is done with the reference to grid lines. When the grid lines are given in the drawing, setting out are done with reference to these grid lines using any type of technique means Suring angles or distances. In the absence of any kind of grid lines detail first the location is at the site. Considering other requirements of usage and setting out is done with reference to any base line or permanent structure. In site the base line has marked in the side of the Moors road and all grid lines are marked on around of the boundary wall. The accuracy of setting out is depending on the usage and for which the structure is used. The method of setting out is depend considering the accuracy required and the measuring instruments avai...

Store Management

Store Management is an important aspect in a construction site. Material requirement should be calculated and the orders should be placed in advance so that material is readily available when work begins. The site stores in this site mainly manage receiving, issuing and storing of material and the maintenance of plant & equipments. Characteristics Of A Well Managed Store Availability of materials whenever required The storage quantity should neither be too much as it would increase the storage cost and the material may get deteriorated. On the other hand the stock levels should not be too low as a material shortage may lead to delays of the project. The optimum may vary from site to site, item to item or supplier to supplier. Yet it is a good practice to keep one week’s requirement in stock. Material should be stored in such a manner that they are easily accessible, not subjected to environmental damages and would not obstruct the site traffic. Using the FIFO basis in i...

Machinery At Site

Image
Machinery Use At Road Project There are many operations to be done in a construction project. Such as demolishing excavation of Earth, transport of material, cleaning etc. for that, most of these operation machines are used Different machines are used difference purpose. The selecting of machinery is done accordingly Nature of work Method of construction Time allowed for the work Earth Moving Equipment Almost all civil engineering project, start with earth excavating work on earth filling even for project where only earth filling is involved. It is necessary to excavate earth from other location for that various types of machines equipment general used such as, Excavators Excavators are very popular earth machine equipment it is mainly using for demolishing work & excavation. There are two types of the feet excavators. Hydraulically powered excavators Cable excavators Hydraulically powered excavators The conventional shovel ex...

Process Analysis For– Asphalt Concrete Surfacing and Concrete Structures

Image
Process Analysis For– Asphalt Concrete Surfacing   Process Analysis For Concrete Structures

METHOD OF INTERNAL & EXTERNAL PLASTERING ON BRICK WALLS & CONCRETE SURFACES

Method of Plastering. Internal plastering on surfaces of brick and concrete. External wall plastering. Soffit plastering / Soffit finishing with cement based easy plaster material and wall putty. Improving joint of brick walls & structural concrete joints. Internal Plastering on surfaces of Brick and Concrete. Surface where plastering is to be done will be cleaned. Level pegs on walls will be fixed with reference to the off lines to brick walls set out in floors. (Using centre plumb bob and nylon thread). All the brick walls will be watered before pasting mortar on walls. First coat mortar filling (1:4 Cement and Sand) upto 15 mm will be applied on surfaces where required mortar thickness exceed 25mm. Walls and columns will be plastered 1:4 Cement and Sand to achieve semi rough finished surface. Vertical joint of structural columns / walls & brick walls will be treated by fixing 200mm width chicken mesh with wire nails / concre...

METHOD OF EXCAVATION

EXECUTION OF WORK Demarcate the excavation line with working space. Shall obtain the written approval from employee to start excavation work. Shall thoroughly explain necessary details to excavator operators to get a smooth Work done and avoid less or over excavation. engineer shall continuously monitor the levels while going on the excavation   SEQUENCE OF WORK Removal of surface soil and debris are carried out and clean the site. Considering the area and volume to be excavated and the different levels of excavations in ground Reservoir excavation work shall carried out in two or three places simultaneously. In the Ground Reservoir , excavation work shall reach up to the required level in one time. In the Back Wash Recovery Tank excavation work shall reach up to about 3.0m level in First phase and in 2 nd phase shall reach up to final required level.   Transporting soil Excavated soil will be transported out from the site and soil...

METHOD OF BRICK MASONRY WORK

Method Statement This method statement will be established for the construction of brick masonry walls and the related work which are to be completed with brick walls. Brick masonry walls in the scope of work are 225mm thick & 112.5mm thick brick walls. These brick walls will be built with 1:5 cement sand mixture. Description. Brick walls will be built for internal partition & as well as perimeter walls of the building. All brick walls will be constructed by maintaining the verticality of walls and the location of the wall as per the construction issued Architectural drawings / approved shop drawings for brick walls in each floor. While constructing the brick walls, opening for the doors, windows & services will be provided according to the dimensions of doors, windows & the dimensions for openings shown in the service drawings by allowing cement / sand plaster thickness of 15mm in each side of the opening. Method of Brick Masonry. Method of brick will be...

Quality management methods

Image
  Quality Plan Processes With Reference to the PDCA cycle as the basic concept of quality management system, that emphasizes the continuous improvement in quality towards zero defects through the processes of Plan, Do, Check and Action. Quality Standards ISO 9001 - Quality Management Standard ISO 9001 is the internationally recognised standard for the quality management of businesses. ISO 9001 applies to the processes that create and control the products and services an organisation supplies prescribes systematic control of activities to ensure that the needs and expectations of customers are met is designed and intended to apply to virtually any product or service, made by any process anywhere in the world   Quality tools Some of the recommended tools and techniques that can be used in quality management include: kaizen, Six Sigma, Pareto charts, fishbone diagrams and hoshin kanri, in addition to 5S and total quality management process. ...

PROJECT QUALITY CONTROL: RESPONSIBILITIES

SENIOR PROJECT MANAGER Responsible for Attending Management Review Meetings and progress review meetings. Responsible for timely valuation of work and submission of the invoice to the client. Attending meeting with Client / Engineer and inform the matters discussed to the Director and site staff for the necessary action. Organizing and reviewing 5-S program at site. Taking responsibility for reviewing supplier /Sub-contractor performance and reporting at Management meetings. Reviewing and approving work plans prepared by Construction Manager. Monitoring the standards of workmanship of employees & Providing Work Instruction to the staff including skilled and unskilled workers. Collecting and forwarding data relating training needs of the staff members for management review meetings when necessary. Initiating Training of Personnel and establishing and maintaining records of training given to the employees of all categories. Fixing re...

Method of Plastering

Image
Method of Plastering Internal plastering on surfaces of brick and concrete. External wall plastering. Soffit plastering / Soffit finishing with cement based easy plaster material and wall putty. Improving joint of brick walls & structural concrete joints. Internal Plastering on surfaces of Brick and Concrete Surface where plastering is to be done will be cleaned. Level pegs on walls will be fixed with reference to the off lines to brick walls set out in floors. (Using centre plumb bob and nylon thread). All the brick walls will be watered before pasting mortar on walls. First coat mortar filling (1:4 Cement and Sand) up to 15 mm will be applied on surfaces where required mortar thickness exceed 25mm. Walls and columns will be plastered 1:4 Cement and Sand to achieve semi rough finished surface. Vertical joint of structural columns / walls & brick walls will be treated by fixing 200mm width chicken mesh with wire na...

FORMWORK

Image
Execution of Works Fabrication of formwork Typical form work details to perform the shape, lines, levels, dimensions & quality of concrete surfaces of Beams, Columns, RC Wall & Slab are attached separately in attachments. Permanent brick wall form work will be used for lower ground floor beams, pile caps, sump walls and lift walls where the waterproofing will be done. (Pile caps will not be water proofed) Examples: Pile caps & beams in the sump will be formed with sump base for waterproofing. Ply wood form and brick form, both will be used in the sides of pile caps up to the bottom of ground beams, inner face of ground beams at main entrance & most of the structural elements in other areas in ground floor considering the sequence of water proofing and the sequence of concrete casting. Refer drawings 230M/FW/06 and sheet 1, 2 & 3 in the attachments Materials for Form Work GI pipes, form ties, threaded bars and P-cones will be used to tie & brace the form ...