Posts

Foundation Part 02

Image
Excavation For Pile Cap Shoring is provided around the proposed pile cap with 600mm working space. Excavation is carried out up to certain level by using backhoe. Then excavation was carried out manually. Excavation is very difficult below ground water level. De watering system should be provided. Excavation With Jcb Shoring Is Provided Difficulties in excavation below the ground water level. Difficult to remove the soil Need continuous de watering process Density of soil will increased Erosion or collapse of the sides of the excavation Pile Hacking Pile is casted up to above required level. Then it is broken up to required level. This is known as pile hacking. Top concrete is weaken so pile should be casted above required level. Normally height above required level, it is equal to the diameter of the pile. But during the concreting ensure the concreting whole pile, normally concreting the ground level. Then excavate soil and pile

Setting Out

  Setting out is done to locate the position of the structural parts as in the detailed drawing with geometrical construction. The setting out is done to locate pile position, pile cap, column position, beam bottoms and slab boundary in the site. Setting out is done with the reference to grid lines. When the grid lines are given in the drawing, setting out are done with reference to these grid lines using any type of technique means Suring angles or distances. In the absence of any kind of grid lines detail first the location is at the site. Considering other requirements of usage and setting out is done with reference to any base line or permanent structure. In site the base line has marked in the side of the Moors road and all grid lines are marked on around of the boundary wall. The accuracy of setting out is depending on the usage and for which the structure is used. The method of setting out is depend considering the accuracy required and the measuring instruments availabi

Store Management

Store Management is an important aspect in a construction site. Material requirement should be calculated and the orders should be placed in advance so that material is readily available when work begins. The site stores in this site mainly manage receiving, issuing and storing of material and the maintenance of plant & equipments. Characteristics Of A Well Managed Store Availability of materials whenever required The storage quantity should neither be too much as it would increase the storage cost and the material may get deteriorated. On the other hand the stock levels should not be too low as a material shortage may lead to delays of the project. The optimum may vary from site to site, item to item or supplier to supplier. Yet it is a good practice to keep one week’s requirement in stock. Material should be stored in such a manner that they are easily accessible, not subjected to environmental damages and would not obstruct the site traffic. Using the FIFO basis in i

Machinery At Site

Image
Machinery Use At Road Project There are many operations to be done in a construction project. Such as demolishing excavation of Earth, transport of material, cleaning etc. for that, most of these operation machines are used Different machines are used difference purpose. The selecting of machinery is done accordingly Nature of work Method of construction Time allowed for the work Earth Moving Equipment Almost all civil engineering project, start with earth excavating work on earth filling even for project where only earth filling is involved. It is necessary to excavate earth from other location for that various types of machines equipment general used such as, Excavators Excavators are very popular earth machine equipment it is mainly using for demolishing work & excavation. There are two types of the feet excavators. Hydraulically powered excavators Cable excavators Hydraulically powered excavators The conventional shovel ex

ABC & ASPHALTING

Image
  Aggregate Base Course (ABC)   Normally construction of ABC shall be commenced after completing of Sub Base and the drainage works. Aggregate Base Course is a mixture of various sizes of aggregates and quarry dust in it. Normally aggregates of 37.5mm, 20mm, and 10mm… are included. In this project, the thickness of the ABC layer is 225mm. The motor grader is used to laying ABC. Normally the road has a cross fall of 3% from the centre the motor grader can be used to blade the road as required. After placing it shall be compacted well using the rollers and the compaction shall be tested. Degree of compaction should be 98% or more. Where (0-40 mm) ABC material has to be spread on a sub-base, the surface of sub-Base should be cleared from any extraneous matter. The ABC material was spread after checking all necessary testing like sieve analysis. After checking the underlying layer for damages or deficiencies, ABC material layer was spread in layers not exceeding 225mm &am

Survey & levelling

Image
    Preliminary work in road construction is surveying & leveling works. This consists of Traverse Survey, TBM Survey, and Centre Line Setting out, Centre Line marking, Cross Section Survey and Submittal of Drawings. Traverse Survey At the commencement of contract all the basic traverse points will be checked and if any are found to be missing or appear to have been disturbed, necessary arrangements should be made to re-establish the points and traverse survey is carried out after that. Establishing TBMS We did not use survey Department bench marks .The permanent concrete cube was selected to permanent bench mark. It height was assumed hundred meters. But this point is not sufficient for construction purposes. So reference to this point Temporary bench marks (TBM) should be established. TBMs are used to transfer reduce levels in road construction. Temporary bench marks should be established at the rate of four per km and also at or near all structures. When establishi

Industrial Safety & Welfare Part 01

Image
  Safety is very important for any construction firm. As Engineers we must consider safety first. It means care about accident earlier and takes some action to avoid damages. It is very important to identified hazards involved in the various operations, which are carried out during the construction phase of project. Some accidents can be fatal and some can results in permanent or partial disable. Safety precaution have been taken at site in order to avoid unexpected accident. Labours are instructed to use safety instruments which they are working. It may be difficult to find an accident free construction site some of the accidents are fatal and some results in permanent complete or partial. People began to realize that occupational accidents had economic as well as physical consequences unexpected accidents and injuries affected to construction as follows. Working time loss by the injured person. Working time loss witness and the accidents investigations. Production st