Method Statement for Construction of Turfing

1. Introduction and General Information

This method statement provides the details of materials, equipment, procedure and relevant documents grass sods on the embankment, including quality control verifications, measurement verifications, and also the safety precautions to be implemented at site for this work.

1.1. Location of Works

The location of the grassing will be selected by consultation with Engineer.

2. Materials

The major materials used for turfing work, but are not limited to the following.

* Grass Sods

* Water

*Top soil

*Fertilizer (if required)

3. Equipment

The major equipment used for the ground preparation of sod fixing and providing grass cover, but are not limited to the following.

* JCB,

*Tractor & Trailer

* Water Bowser

*Other minor tools

4. Safety Management and Control

Safety precaution will be taken complying with the Road Work Traffic Control Manual. Every precautions will be taken avoid any damages to adjoining properties.

5. Method and Procedures

Following procedure will be used to sod fixing on the embankment.

5.1 The locations of the embankment slop and earth drains will be set out complying with the construction drawings, schedules or instructed by Engineer.

5.2 Then earth drain excavation will be done after getting the engineers consent by mean of manually or mechanically. All the necessary precautions will be taken to avoid any damages to adjoining properties during excavation.

5.3 After getting the approval from the engineer for the embankment slop, top soil will be speeded uniformly on the embankment.

5.4 Grass sods will be of living vigorous growth and contained in suitable sods and free from weeds. The Engineer’s approval for grass sods will be taken prior to lay the grass sods on the embankment.

5.5 After laying and joint filling, sods shall be tamped in an approved manner to provide an even surface. Turefed area shall be cure until the grass cover is grown.

6. Quality Control

Several inspections and verifications will be carried out as described in the above method and procedures to ensure that the steps of the procedure are fully complied with during grass laying.

7. Measurement Control

Site measurements will be carried out and recorded during the course of the works as indicated in the above procedures. The measurements of turfed are will be taken off by means of joint site measurements.

Comments

  1. There are many artificial grass makers in town and I know of one which gives good service and maintain artificial grass.

    ReplyDelete
  2. This content is written very well. Your use of formatting when making your points makes your observations very clear and easy to understand. Thank you. refurbishment company London

    ReplyDelete
  3. This is such a useful blog with nice information and images. This is giving excellent knowledge to the viewers. Thank you so much friend to share post like this.

    SOD Installation Atlanta

    ReplyDelete
  4. Very useful article information on Artificial Grass. Thanks for sharing. From Artificial Grass Manufacturer

    Artificial Grass Service Manufacturer

    ReplyDelete
  5. Geocell, a cutting-edge cellular confinement system, is transforming the Geocells In Road Construction and infrastructure landscape by offering unmatched soil stabilization, erosion control, and load-bearing capabilities. Designed to enhance durability, reduce maintenance costs, and provide sustainable solutions for roads, embankments, and retaining walls, Geocell is the preferred choice for modern civil engineering projects.

    ReplyDelete

Post a Comment

Popular posts from this blog

Field Density Test

ABC & ASPHALTING

Store Management