Method Statement for Road Marking
1. Introduction and General Information
This method statement consists of construction procedures of Road Marking, including material & machineries to be used, method of constructions, quality control test & verifications, and also the safety precautions to be implemented at site.
1.1. Location of Works
Road marking location will be decided as per the road marking drawings issued by the Engineer.
2. Materials
The major materials used for the road marking.
- DJ Thermo line thermoplastic road marking materials.
- Glass beads.
The major equipment used for Road marking includes, but are not limited to the following.
- Road Marking Machine.
- Gas.
- Rope.
- Chisel.
- Cleaning equipment
- Small Tools.
Safety precaution will be taken complying with the Traffic & Safety Plan. Every precaution will be taken to avoid any accidents & damages to adjoining properties, workers, and road users.
All workers will be advised to wear helmets, boots, and gloves while working. There will be a stand by vehicle near site always if needed in a case of accident.
The safety officer inspects several times to inspect safety matters.
5. Method and Procedures
The method and procedures for Road marking will follow the steps below. Flow chart is also provided in appendix A.
5.1 Center line will be set out and get approvals about the center line before commencement of line marking.
5.2 Road surface shall be cleaned manually using wire brush and wash the surface where necessary.
5.3 As per the approved road marking design the road marking lines & symbols will be set out means of white chalk and approval will taken by Engineer.
5.4 The thermoplastic material is heated in the range of temperature around 170 ~ 200 C and maintain in the range during the entire laying process.
5.5 After getting the approval of the temporary marking on the asphalt surface permanent marking shall be carried out by considering required color. This machine has the facility of adding glass beads in to the paint while painting.
5.6 All roads marking shall be protected from traffic until the marked paint get dry.
6. Quality Control
To ensure that the steps of the procedure are fully complied with the activities such as setting out, temporary marking , permanent painting etc. certain inspections and verifications will be carried out as described in the above procedures.
Labels: Highway Engineering, Method Of Statement, Road Projects
20 Comments:
Wow, I didn't know there was a "method" to road marking. It always seemed like a fairly straight forward, simple labor project. This paints it as kind of an art form. Thiago | http://www.austraklinemarking.com.au
Thank you for this MS. It helped me to analysis the risk associated
thanks for info..it helped me a lot..tq
This is great one to see your blog last time I see same design to my friend constraction building in chennai. Majorly used Aluminium scaffolding equipment used for glass room design. Really very gud looking.
Nice Blog, Really Good Content, Really Helpfull for us, I have also a Some Great Content For you Guys, so just go through and take benefit of asphalt services
asphalt sealcoatin
asphalt repair
asphalt overlay
brick paver driveways
cement curbing
line striping
thermoplastic markings
concrete sidewalks
bingo! i got it
I read this article, it is really informative one. Your way of writing and making things clear is very impressive. Thanking you for such an informative article. Line Removal Service in Brisbane
This comment has been removed by the author.
Thanks to this article about are the information it will be helpful for road marking works.
PVDF Engineering parts
I’ve desired to post about something similar to this on one of my blogs and this has given me an idea. Patio Pavers Boca Raton Cool Mat.
What is DJ Thermo line?
Augustine thanks for sharing this! My extensive google search has now been recently paid for using quality insight to talk about together with our relatives. driving instructors
Civil Projects: Method Statement For Road Marking >>>>> Download Now
>>>>> Download Full
Civil Projects: Method Statement For Road Marking >>>>> Download LINK
>>>>> Download Now
Civil Projects: Method Statement For Road Marking >>>>> Download Full
>>>>> Download LINK
Civil Projects: Method Statement For Road Marking >>>>> Download Now
>>>>> Download Full
Civil Projects: Method Statement For Road Marking >>>>> Download LINK
>>>>> Download Now
Civil Projects: Method Statement For Road Marking >>>>> Download Full
>>>>> Download LINK Dq
PMP Classroom Training from expert practitioners to pass the PMP® exam on your 1st attempt with best practices
PMP CLASSROOM TRAINING
I like this blog's detailed method for road marking. If you need line marking in Gold Coast, check out Kenex expert solutions to keep roads safe and well-organized.
This comment has been removed by the author.
This comment has been removed by the author.
This comment has been removed by the author.
Your blog about road marking is fantastic! I appreciate how you explain everything clearly. It's super helpful for anyone looking for info on line marking Brisbane Great job!
Post a Comment
Subscribe to Post Comments [Atom]
<< Home